There are roughly four steps in the process of SMT processing: solder paste printing → component placement → reflow soldering → AOI.

Of course, it can be further subdivided: feeding → solder paste printing (side A) → component placement (side A) → visual inspection in front of the reflow soldering → reflow oven → solder paste printing (side B) →component placement (side B) →visual inspection in front of the reflow soldering → reflow oven → inspection after reflow soldering →split board → download → FQA inspection → production inspection → FT test → BT test → CIT test


Each step is described in detail below:

1. Feeding

Solder paste printing manufacturing services

Feeding means that after the factory receives the customer's BOM, the corresponding program will be written, and then the item number and item name will be listed in the corresponding machine. At this time, the warehouse can arrange the materials of the project to be produced in advance according to the plan, and then the material production personnel will put the materials into the corresponding machine according to the material number set in the machine. After the production material personnel have loaded the materials, the inspectors will coordinate to check whether there is any inconsistency in the material numbers, and sign the material on the material feeding record. PQA will randomly check the material feeding situation when patrolling the line.


1.1 When a plate of materials is used up and a new plate needs to be replaced, it will be placed in the wrong place if the personnel do not pay attention. At present, all materials are required to be confirmed by both the production staff and the inspector before going online.


1.2 When the incoming part number is handwritten, there will be quality risks. The handwritten part number itself may be wrong, and the person checking the part number may mistake the part number for another part number.


1.3 Some production reject parts are not easy to distinguish when they are recycled, need to define the time used up.


1.4 When the material is relatively small and needs to be patched separately at each station, the corresponding personnel are required to confirm when reposting the label.


2. Solder paste printing


Solder paste printing suppliers


The solder paste must be warmed before use, and the opening time must be recorded after opening and must be stirred evenly before it can be used online. At present, the control method of solder paste control printing is an important parameter to record the printing results, which cannot be deviated from the defined range, that is, blade pressure, demolding speed, demoulding distance, printing speed, automatic cleaning frequency, automatic cleaning speed, etc. OP's request is two hours of cleaning, manual cleaning of the stencil once, and a cleaning record.


The final monitoring method for the effectiveness of the solder paste machine is to measure whether the thickness of the solder paste is within the standard range, and use the CPK value to monitor the effectiveness of the MPM/DEK. However, the monitoring method for the solder paste offset is only to have the OP look at the magnifying glass, and if the board has problems such as continuous soldering and offset after reflow soldering, it will go back to investigate whether the solder paste printing is the problem.


2.1 The solder paste is not used as required.


2.2 The printing problems were not fed back to the relevant personnel in time for adjustment.


2.3 Although the height of the solder paste after printing meets the requirements of the range, when CPK1.67 or 7 points in a row is on one side of the center line, the employees fail to report the problem in time. Even after the problem is reported, the relevant craftsmen are not sure how to adjust it. 


3. Component placement



Solder paste printing factory


The component feeder and the PCB are fixed. The placement head moves back and forth between the feeder and the PCB, and the components are taken out from the feeder. After adjusting the position and orientation of the components, they are placed on the PCB.


3.1 When some holes of the suction nozzle are blocked, and the appearance and color of the material are different, it will cause the machine to throw material and so on.


3.2 When the material belt is not placed horizontally, the material belt is broken, and the viscosity is too high, which is blamed on the supplier.


3.3 When the incoming material is inconsistently placed in the material belt, or the incoming material does not match the size of the material tray, it will also affect the quality of the patch.


3.4 The person inspecting before the reflow soldering should be able to supervise the problem. If it is above the 0603 level, a little offset will not affect the product quality, but if it is a 0.5PIN component, in principle, no offset is allowed.


4. Reflow soldering



pcb board assembly manufacturing services


In the process of hot air reflow soldering, the solder paste needs to go through the following stages, the solvent is volatilized; the flux removes the oxides on the surface of the soldered parts; the solution of the solder paste is reflowed to cool and solidify the solder paste.


4.1 Preheating zone


Preheat the PCB and components to achieve equilibrium, while removing moisture and solvent volatilization in the solder paste. It is relatively mild, and the thermal shock to the components is as small as possible. If the temperature rises too fast, it will cause damage to the components, such as cracking of the multilayer ceramic capacitor. At the same time, it will also cause solder spatter, resulting in the formation of solder balls and insufficient solder joints in the non-soldered areas of the entire PCB.


4.2 Heat preservation area


Ensures that the solder is completely dry before reaching the reflow temperature, and also acts as flux activation to remove metal oxides from components, pads, and solder powder. The time is about 60~120 seconds, depending on the properties of the solder.


4.3 Reflow area


The solder in the solder paste causes the gold powder to begin to melt and flow again, replacing the liquid flux to wet the pads and components. This wetting action causes the solder to spread further, with a wetting time of 60 to 90 seconds for most solders. The temperature of reflow soldering should be higher than the melting point temperature of solder paste, generally 20 degrees higher than the melting point temperature to ensure the quality of reflow soldering. This area is also sometimes divided into two zones, the melt-off and reflow zones.


4.4 Cooling area


The solder solidifies as the temperature decreases, so that the components and the solder paste form a good electrical contact, and the cooling speed should not be too different from the preheating speed.


5. Split board



pcb board assembly manufacturer


At present, a splitting machine is used, which adopts rotary cutting, but sometimes the factory will cut the auxiliary board by hand with scissors due to production capacity. When it is necessary to cut by hand, a document is formulated to inform the OP of the cutting order, and when the cutting is completed, the effect of the inspection is to prevent the phenomenon that the last part of the board edge is broken by hand.


6. Test



pcb board assembly suppliers


For download, BT, FT and other workstations, it is necessary to check whether the version used is consistent with the customer's work order, and whether the fixture and power supply used in the operation are implemented as required. This is a software test, and the factory can keep the data for later inspection. As for the CIT station, because we currently have many test items, many items in the test process need to be judged manually. This item is prone to missed tests. In the case of tight production capacity, other departments will put forward suggestions such as sampling tests.


In the current test control method, the code name of the CIT tester is written on the board, so that people in the latter stage can judge whether the board has undergone the CIT test, but in general, because the staff judges whether it passes, if the staff does not understand the following , false detection may occur. Most of the bad judgments in the test are done manually, and it will be more accurate if it can be imported into the automatic mode.


7. Inspection



pcb board assembly factory


The inspection standard is the second-level standard of IPC-610D. At present, due to the inconsistent mastery of the standard by factory personnel. That is, a magnifying glass of 10 times is enough for inspection, but for doubtful places, a better magnifying glass is needed for arbitration. For example, the reliability and standard of the solder of L-shaped pins are defined as the root of the pin. The current equipment cannot see the tinning of the root and rear end of the L-shaped pins, but it is only based on the experience of personnel whether it is bad.


Hot Tags: SMT Process manufacturer, Split board manufacturing services, Solder paste printing manufacturing, pcb board assembly suppliers, Inspection PCB, surface mount technology, SMT processing, Test PCB, reflow soldering,  Customized Component placemen, factory, quotation, cheap

Table of Content list
Sign up for our newsletter

PCB Fab

PCB Assembly

Capabilities

CONTACT US
General Inquiry
Email: sales@syspcb.com
Phone: +86-0769-82201689
Fax: +86-0769-87799518

Tech Support
Email: tech@syspcb.com
Phone: +86-0769-82201689
SOCIAL NETWORKS
Copyright © 2024 SYS Technology Co., Ltd. All Rights Reserved.|Privacy policy|sitemap
We use cookies to enable all functionalities for best performance during your visit and to improve our services by giving us some insight into how the website is being used. Continued use of our website without having changed your browser settings confirms your acceptance of these cookies. For details please see our privacy policy.
×